% complete in Microsoft Project: what it really measures
Microsoft Project's % complete measures elapsed time, not work done. Mistaking it for real progress produces reassuring, wrong schedules.
Microsoft Project offers several percentages, and they do not say the same thing. The most used, % complete, is also the most misunderstood.
% complete measures duration
% complete shows the share of the planned duration that has elapsed. A three-week task with two weeks gone shows 67%, whether or not the work has progressed.
% work complete measures hours
% work complete compares hours done with hours planned. On our prototype, 28 of 40 hours are done: 70%. It is closer to reality, but it assumes the initial estimate was right.
Remaining work tells the truth
The only truly useful information is what the person doing the work gives: how many hours are left. Here, 12 hours. If they announced 20 hours, both percentages would stay the same, and the delay would go unnoticed.
Key points
- % complete: elapsed time, not work done;
- % work complete: hours done, based on the initial estimate;
- remaining work: the up-to-date estimate, the only one that says whether the task will hold.